Commissioning & Start-up Plan

Systematic commissioning sequence from pre-commissioning punch-list closure through utility start-up, catalyst loading, plant start-up, to the 72-hour Performance Guarantee Test.

M20–M21

Pre-Commissioning

Punch-list, loop checks

M21–M22

Utility Commissioning

IA, CW, DM, Steam, Power

M22–M23

Catalyst & Start-up

Loading, drying, first fire

M23–M24

PG Test

72-hr continuous test

Mandatory — Must complete before start-up
Conditional — Complete before acid introduction
Recommended — Best practice
St.Check Item
All welding complete, NDE accepted, NCRs closed
Catalyst support grids installed and leveled
Refractory lining cured (minimum 72 hrs)
All flanged joints torqued to spec
Instrument loop checks complete (100%)
Interlock function test complete
Insulation and cladding complete
Painting complete (touch-up after hydrotest)