SECTION 6.0

Simon India

Construction Costs

Piling, civil works, structural steel, and balance of plant — based on actual estimates for the 3,000 MTPD SAP project.

₹ 22.50 Cr

Piling Works

₹ 26.00 Cr

Civil — Pile Cap, Foundation & Roads

₹ 15.00 Cr

Structural Works

₹ 1.00 Cr

Balance of Plant (BOP)

Total Construction Cost₹ 64.50 Cr

6.1 Piling Works₹ 22.50 Cr

ItemCost (₹ Cr)
Piling — 1,500 Nos.22.50
Subtotal22.50

6.2 Civil — Pile Cap, Foundation & Roads₹ 26.00 Cr

ItemCost (₹ Cr)
Pile Caps & Equipment Foundations14.00
Building Foundations & Structures5.00
Internal Roads & Paving4.00
Underground Drains & Trenches3.00
Subtotal26.00

6.3 Structural Works₹ 15.00 Cr

ItemCost (₹ Cr)
Pipe Racks & Sleepers5.50
Equipment Platforms & Access4.50
Structural Steel for Buildings3.00
Miscellaneous Structures2.00
Subtotal15.00

6.4 Balance of Plant (BOP)₹ 1.00 Cr

ItemCost (₹ Cr)
BOP — Miscellaneous1.00
Subtotal1.00

6.5 Key Suppliers & Contractors

Civil & Structures

Priya Const.
Jolly Const.
KCC
HES Const.

Structures:

Balajee
Priya Const.
Zamil

Piping

Enmax
SIL — Sparkon
Samantaray
Victor

IBR piping: Enmax, SIL-Sparkon | Non-IBR: SIL-Sparkon, Victor

Fabricated Equipments

SIL — Sparkon
Enmax
Galiakotwala
Thermal Systems
Jasubhai

Blowers & Pumps

Howden (blowers)
Eiger
Wilfley
Chemlin
Chas Lewis
Process Pumps
KSB
KBL

Burners & Heat Exchangers

Thermal Systems
SIL — Sparkon
Enmax
Galiakotwala
Jasubhai

Construction Methodology

Construction will follow a modular approach with maximum pre-fabrication at SIL's in-situ fabrication yard (EIL-approved with best-in-class machinery). Piling will be accelerated by doubling the contractors. Peak construction manpower is estimated at 150–200 workers (RTC established, operating in shifts). Execution through heavy duty cranes, man-lifters and industrial machinery. Safety management will follow OHSAS 18001 standards with zero-incident targets.