SECTION 6.0

Piling, civil works, structural steel, and balance of plant — based on actual estimates for the 3,000 MTPD SAP project.
₹ 22.50 Cr
Piling Works
₹ 26.00 Cr
Civil — Pile Cap, Foundation & Roads
₹ 15.00 Cr
Structural Works
₹ 1.00 Cr
Balance of Plant (BOP)
| Item | Cost (₹ Cr) |
|---|---|
| Piling — 1,500 Nos. | 22.50 |
| Subtotal | 22.50 |
| Item | Cost (₹ Cr) |
|---|---|
| Pile Caps & Equipment Foundations | 14.00 |
| Building Foundations & Structures | 5.00 |
| Internal Roads & Paving | 4.00 |
| Underground Drains & Trenches | 3.00 |
| Subtotal | 26.00 |
| Item | Cost (₹ Cr) |
|---|---|
| Pipe Racks & Sleepers | 5.50 |
| Equipment Platforms & Access | 4.50 |
| Structural Steel for Buildings | 3.00 |
| Miscellaneous Structures | 2.00 |
| Subtotal | 15.00 |
| Item | Cost (₹ Cr) |
|---|---|
| BOP — Miscellaneous | 1.00 |
| Subtotal | 1.00 |
Structures:
IBR piping: Enmax, SIL-Sparkon | Non-IBR: SIL-Sparkon, Victor
Construction Methodology
Construction will follow a modular approach with maximum pre-fabrication at SIL's in-situ fabrication yard (EIL-approved with best-in-class machinery). Piling will be accelerated by doubling the contractors. Peak construction manpower is estimated at 150–200 workers (RTC established, operating in shifts). Execution through heavy duty cranes, man-lifters and industrial machinery. Safety management will follow OHSAS 18001 standards with zero-incident targets.