SECTION 16.0

Health, Safety & Environment management framework for the 3,000 MTPD Sulphuric Acid Plant EPC project — targeting zero incidents across 2.5 million construction man-hours.
Target: ZERO Lost Time Incidents
Simon India is committed to achieving zero LTI across the entire 24-month EPC execution period, covering an estimated 2.5 million construction man-hours with a peak workforce of 800+ personnel.
0
LTI Target
2.5M
Man-hours
800+
Peak Workforce
| KPI | Target |
|---|---|
| Lost Time Injury Frequency Rate (LTIFR) | Zero |
| Total Recordable Incident Rate (TRIR) | < 1.0 |
| Near Miss Reporting Rate | > 50/month |
| Safety Training Hours | > 4 hrs/person/month |
| Safety Audit Score | > 90% |
| Unsafe Act/Condition Reports | > 100/month |
| First Aid Cases | < 5/month |
| Environmental Incidents | Zero |
Mandatory 8-hour safety induction for all new personnel before site entry. Covers site rules, hazard awareness, PPE requirements, emergency procedures, and first aid basics. Refresher every 6 months.
Daily 15-minute pre-work briefing by supervisor covering day's activities, specific hazards, control measures, and lessons from recent incidents. Attendance recorded and tracked.
Trained observers conduct peer observations. Focus on at-risk behaviors. Positive reinforcement for safe behaviors. Monthly analysis of observation data to identify trends.
Monthly recognition for best safety performance by crew. Quarterly safety awards. Zero-incident milestones celebrated. Penalty system for repeat offenders.
Joint safety walk by Construction Manager, HSE Manager, and Client representative every Wednesday. Findings documented, corrective actions tracked to closure within 48 hours.
Formal meeting chaired by Project Manager. Attendance: all discipline leads, subcontractor supervisors, worker representatives. Minutes distributed within 24 hours.