SECTION 17.0

Simon India

Quality Assurance Plan

Comprehensive QA/QC framework covering Inspection & Test Plans, welding procedure qualifications, NDE acceptance criteria, and document review workflow for the 3,000 MTPD Sulphuric Acid Plant EPC project.

Hold / Witness / Review Point Legend

HHold Point — Work stops until witnessed & approved
WWitness Point — Notified 24 hrs in advance, may proceed if not attended
RReview — Records reviewed, presence not required
Not applicable
#Activity / CheckReferenceAcceptance CriteriaCOTRecords
1Review of material test certificates (MTC)ASME SA-516 Gr.70 / SA-240Chemical composition & mechanical properties per specRRRMTC, Mill Certificates
2Raw material inspection — plate UT scanningASME SA-578 / SA-435No lamination, UT acceptance per Level BWRWUT Report
3Marking, cutting & edge preparationApproved drawingDimensions within tolerance, bevel angle ±2.5°RRDimensional Report
4Fit-up inspection before weldingWPS / Approved drawingRoot gap, alignment, tack weld quality per WPSWWWFit-up Report
5Welding — longitudinal & circumferential seamsQualified WPS per ASME Sec. IXVisual acceptance per ASME Sec. VIII UW-35WRWWeld Log, WPS/PQR
6NDE — 100% RT of all pressure seamsASME Sec. V Art. 2RT acceptance per ASME Sec. VIII UW-51(b)HWHRT Film, Reader Sheet
7NDE — UT of nozzle-to-shell weldsASME Sec. V Art. 4UT acceptance per ASME Sec. VIII App. 12WRWUT Report
8Post-Weld Heat Treatment (PWHT)ASME Sec. VIII UCS-56Holding temp 595–650°C, rate per thickness, chart recordingHWHPWHT Chart, Thermocouple Layout
9Hardness testing after PWHTASME Sec. VIII UCS-85≤225 HBW for CS, per material specWRWHardness Report
10Hydrostatic testASME Sec. VIII UG-99Test pressure = 1.3 × MAWP, 30-min hold, no leak/deformationHHHHydrotest Report, Pressure Chart
11Final dimensional inspectionApproved GA drawingAll dimensions within drawing tolerancesWWWDimensional Report
12Painting & surface protectionProject painting specSa 2.5 surface prep, DFT per specRRRPainting Report, DFT Records
13Final inspection & releaseAll aboveAll NCRs closed, documentation completeHHHRelease Certificate, MDR

Note: ITPs shown are proposal-stage templates (Rev 0). Detailed ITPs will be finalized post contract award in consultation with PPL QA/QC team and the appointed TPI agency. Additional ITPs will be developed for E&I equipment, rotating equipment, and site construction activities.