SECTION 21.0

Simon India

Scope of Work

Comprehensive delineation of EPC contractor's scope for the 3,000 MTPD Sulphuric Acid Plant with HRS and CPP integration.

10

Disciplines

77

Items Included

17

Items Excluded

94

Total Scope Items

Toggle to show/hide excluded (client scope) items

Basic Engineering Package (BEP) from selected licensor (MECS/NIUIF)

Complete process design, P&IDs, equipment datasheets, catalyst specification, and process guarantees.

EPC

Proprietary equipment supply (HRS Tower, HRS Boiler, HRS internals, mist eliminators)

All proprietary items as per licensor scope split. Delivered CIF site.

EPC

Catalyst supply — V₂O₅ (Cs-promoted) for all 5 converter beds

Catalyst quantity as per licensor recommendation. Includes initial charge + commissioning top-up.

EPC

Licensor supervision during erection, commissioning & start-up

Licensor deputes 2–3 specialists for critical phases. Duration: ~4 months.

EPC

Performance Guarantee Test supervision

72-hour PG test at 100% capacity under licensor supervision.

EPC

Licensor's process royalty / license fee

One-time license fee included in EPC contract value.

EPC

Licensor's extended warranty beyond 12 months

Standard warranty 12 months from mechanical completion. Extended warranty to be negotiated separately.

Client

21.2 Scope Boundary Summary

InterfaceEPC ScopeClient ScopeDemarcation Point
Process PipingAll piping within SAP plot boundaryInterconnecting piping to existing plantsFirst flange pair at plot boundary
Electrical PowerSAP substation, all internal distributionPower supply cable to SAP substationIncoming terminal of SAP HT switchgear
Cooling WaterCooling tower, CW pumps, internal CW pipingMake-up water supply to CW basinCW basin inlet nozzle
DM WaterDM water tank, pumps, internal distributionDM water supply to SAP DM tankDM tank inlet nozzle
Instrument AirAir compressor, dryer, receiver, distributionNone (self-contained within SAP)N/A — fully within EPC scope
EffluentInternal drains, neutralization pit, sump pumpsEffluent pipeline from SAP to ETPSAP plot boundary manhole
Steam ExportHP/LP steam headers within SAPSteam pipeline to downstream usersSteam header flange at plot boundary
Control SystemDCS/SIS within SAP, all field instrumentsIntegration with existing plant DCSOPC/Modbus gateway at SAP control room
Roads & AccessInternal roads within SAP plotApproach road to SAP plot boundarySAP plot gate
Statutory ApprovalsTechnical documentation supportAll statutory approvals & permitsEPC provides docs, client obtains approvals

21.3 Key Assumptions & Conditions

1.

Client shall provide uninterrupted access to the SAP plot area from the date of contract award.

2.

Construction power (minimum 500 kVA) and water supply (minimum 50 m³/day) shall be made available by client at SAP plot boundary.

3.

Geotechnical investigation report and topographic survey data shall be provided by client within 30 days of contract award.

4.

Environmental Clearance (EC) and all statutory approvals shall be in place before commencement of construction activities.

5.

Free-issue materials (if any) shall be delivered to site as per the agreed schedule. Any delay shall entitle EPC contractor to schedule extension.

6.

The EPC price is based on current GST rates. Any change in tax structure shall be to client's account.

7.

Force majeure events (natural calamities, pandemic, war, government restrictions) shall entitle schedule extension and cost adjustment as per contract terms.

8.

Client shall nominate a dedicated Project Coordinator for timely review and approval of engineering documents (target: 15 working days per submission).

9.

All imported equipment shall be cleared through Paradeep port. If port is unavailable, additional logistics cost for alternate port shall be to client's account.

10.

The scope and price are based on the design basis and site conditions as known at the time of proposal. Any change in design basis shall be subject to variation order.

Note: This scope of work is indicative and subject to finalization during contract negotiations. All items marked "Client" are excluded from the EPC contract price.