SECTION 18.0

Simon India

Battery Limits & Tie-in Points

Detailed scope demarcation between EPC contractor and client at each tie-in point. Toggle acceptance to see cost impact of scope changes.

All Tie-in Points Accepted — No Additional Cost Impact

₹0.00 Cr

Additional Cost

21/21

Accepted

TI-P-001

Molten Sulphur Feed

CRITICAL PATH

Molten sulphur supply from existing sulphur storage/melting facility to new SAP battery limit at sulphur pit inlet.

Existing Sulphur Melting PlantNew SAP — Sulphur Pit Inlet
Size:6" NB
MOC:CS with steam jacketing
Design:150°C / 3 bar(g) / 250 TPD max
EPC Scope:

From battery limit flange to sulphur pit. All piping, valves, instruments within SAP plot.

Client Scope :

Molten sulphur pipeline from existing plant to battery limit flange. Steam tracing supply for jacketed line.

TI-P-002

Product Acid (98.5% H₂SO₄) Dispatch

CRITICAL PATH

Product acid pipeline from new SAP acid storage tanks to existing acid loading/dispatch facility or product pipeline header.

New SAP — Acid Storage Tank OutletExisting Acid Dispatch / DAP Plant
Size:8" NB
MOC:CS (Sch 40) with PTFE lining
Design:Ambient / 5 bar(g) / 3,000 TPD
EPC Scope:

Acid storage tanks, pumps, and piping up to battery limit flange.

Client Scope :

Pipeline from battery limit to existing dispatch/DAP plant. Any modifications to existing receiving facility.

TI-P-003

Oleum (20–25% SO₃) Dispatch

Oleum product pipeline from oleum absorption tower circuit to existing oleum storage/dispatch.

New SAP — Oleum CircuitExisting Oleum Storage
Size:4" NB
MOC:CS (Sch 80)
Design:60°C / 5 bar(g) / 200 TPD
EPC Scope:

Oleum circuit piping and pumps up to battery limit flange.

Client Scope :

Pipeline from battery limit to existing oleum storage. Modifications to existing oleum tanks if required.

TI-P-004

HP Steam Export (40 bar, 400°C)

CRITICAL PATH

High-pressure superheated steam from WHB to existing steam header / turbine generator.

New SAP — WHB Steam DrumExisting Steam Header / TG Set
Size:12" NB
MOC:ASTM A335 P11 (CrMo)
Design:400°C / 42 bar(g) / 85 TPH
EPC Scope:

WHB, steam drum, superheater, and HP steam piping up to battery limit flange. All safety valves, instruments, and controls.

Client Scope :

HP steam pipeline from battery limit to existing header/TG. Any modifications to existing steam system for additional 85 TPH capacity.

TI-P-005

LP Steam Export (4.5 bar, saturated)

Low-pressure steam from economizer / deaerator vent to existing LP steam header.

New SAP — EconomizerExisting LP Steam Header
Size:8" NB
MOC:CS (ASTM A106 Gr.B)
Design:160°C / 5 bar(g) / 15 TPH
EPC Scope:

LP steam piping from economizer to battery limit flange.

Client Scope :

LP steam pipeline from battery limit to existing LP header. Condensate return arrangement.

TI-P-006

BFW Return (Condensate)

Boiler feed water / condensate return from existing condensate system to new SAP deaerator.

Existing Condensate SystemNew SAP — Deaerator
Size:6" NB
MOC:CS (ASTM A106 Gr.B)
Design:105°C / 6 bar(g) / 90 m³/hr
EPC Scope:

Deaerator, BFW pumps, and piping from battery limit flange to WHB.

Client Scope :

Condensate pipeline from existing system to battery limit. Condensate quality to meet BFW spec (conductivity <10 μS/cm).

TI-U-001

Cooling Water Supply

CRITICAL PATH

Cooling water supply from existing CW system / cooling tower to new SAP battery limit.

Existing Cooling TowerNew SAP — CW Header Inlet
Size:24" NB
MOC:CS with cement mortar lining
Design:32°C supply / 42°C return / 4,500 m³/hr
EPC Scope:

CW distribution within SAP plot — headers, branch connections to all exchangers, return header to battery limit.

Client Scope :

CW supply and return pipelines from existing CT to battery limit. Augmentation of existing CT capacity if required (~4,500 m³/hr additional).

TI-U-002

Cooling Water Return

CRITICAL PATH

Cooling water return from new SAP to existing CW return header / cooling tower basin.

New SAP — CW Return HeaderExisting Cooling Tower Basin
Size:24" NB
MOC:CS with cement mortar lining
Design:42°C / 3 bar(g) / 4,500 m³/hr
EPC Scope:

CW return header within SAP plot up to battery limit flange.

Client Scope :

CW return pipeline from battery limit to existing CT basin.

TI-U-003

DM Water Supply

Demineralized water from existing DM plant to new SAP battery limit for boiler make-up.

Existing DM PlantNew SAP — DM Water Tank
Size:4" NB
MOC:SS 304
Design:Ambient / 4 bar(g) / 25 m³/hr
EPC Scope:

DM water storage tank, distribution within SAP plot.

Client Scope :

DM water pipeline from existing DM plant to battery limit. Augmentation of DM plant capacity if required (~25 m³/hr additional).

TI-U-004

Raw Water Supply

Raw water from existing water intake / reservoir to new SAP for CW make-up, service water, fire water.

Existing Raw Water SystemNew SAP — Raw Water Header
Size:8" NB
MOC:CS with epoxy lining
Design:Ambient / 4 bar(g) / 100 m³/hr
EPC Scope:

Raw water distribution within SAP plot — service water, fire water make-up, CW make-up.

Client Scope :

Raw water pipeline from existing system to battery limit. Ensure adequate raw water availability (~100 m³/hr continuous).

TI-U-005

Instrument Air Supply

Instrument air from existing IA system or new dedicated compressor to SAP battery limit.

Existing / New IA CompressorNew SAP — IA Header
Size:3" NB
MOC:CS (galvanized)
Design:Ambient / 7 bar(g) / 500 Nm³/hr
EPC Scope:

IA distribution within SAP plot. If new compressor required, included in EPC scope.

Client Scope :

IA pipeline from existing system to battery limit (if using existing IA). If new compressor provided by EPC, only space and power connection.

TI-U-006

Nitrogen Supply

Nitrogen for purging, blanketing, and inerting from existing N₂ system or new PSA unit.

Existing N₂ System / New PSANew SAP — N₂ Header
Size:2" NB
MOC:CS
Design:Ambient / 8 bar(g) / 200 Nm³/hr
EPC Scope:

N₂ distribution within SAP plot. PSA unit if required.

Client Scope :

N₂ pipeline from existing system to battery limit (if using existing). Power and space for new PSA if required.

TI-E-001

HT Power Supply (33 kV)

CRITICAL PATH

33 kV power supply from existing grid substation to new SAP main receiving substation.

Existing 33 kV SubstationNew SAP — 33 kV Switchgear
Size:2 × 33 kV feeders
MOC:XLPE cable (3C × 300 sq.mm Al)
Design:33 kV / 2 × 15 MVA / 50 Hz
EPC Scope:

33 kV switchgear, transformers (33/6.6 kV), all MCC/PCC within SAP plot. Cable from battery limit to SAP substation.

Client Scope :

33 kV cable from existing substation to battery limit. 2 nos. spare feeder bays in existing 33 kV switchgear. Protection relay coordination with existing system.

TI-E-002

Power Export (TG Output)

CRITICAL PATH

Power export from SAP turbine generator to existing grid / plant distribution system.

New SAP — TG Terminals (11 kV)Existing 11 kV Bus / Grid
Size:11 kV / ~30 MW
MOC:XLPE cable (3C × 630 sq.mm Cu)
Design:11 kV / 30 MW / 0.85 PF / 50 Hz
EPC Scope:

TG set, 11 kV generator breaker, step-up transformer (if required), cable up to battery limit.

Client Scope :

11 kV cable from battery limit to existing bus/grid. Synchronization and protection coordination. Grid connectivity approval from DISCOM.

TI-E-003

Emergency DG Power

Emergency diesel generator power supply for critical loads during grid failure.

New SAP — DG SetNew SAP — Emergency MCC
Size:1 × 1000 kVA DG
MOC:Standard
Design:415V / 1000 kVA / 50 Hz
EPC Scope:

DG set, ATS panel, emergency MCC, cabling — all within SAP plot. Fully within EPC scope.

Client Scope :

Diesel fuel supply arrangement (existing fuel storage).

TI-I-001

DCS Integration with Existing Plant

Data link between new SAP DCS and existing plant central control room / SCADA system.

New SAP — DCS MarshallingExisting Central Control Room
Size:Fiber optic + Modbus/OPC
MOC:Armored fiber optic cable
Design:Redundant communication link
EPC Scope:

New SAP DCS system complete (controllers, I/O, HMI, engineering stations). OPC server for data exchange. Fiber patch panel at battery limit.

Client Scope :

Fiber optic cable from battery limit to existing CCR. OPC client configuration in existing SCADA. Display integration in existing HMI.

TI-I-002

CEMS (Stack Emission Monitoring)

Continuous Emission Monitoring System data link to OSPCB / CPCB online portal.

New SAP — CEMS AnalyzerOSPCB Online Portal
Size:Internet / GSM link
MOC:Standard
Design:SO₂, NOx, PM — real-time upload
EPC Scope:

CEMS analyzer, sampling system, local display, data logger. Internet connectivity to OSPCB portal.

Client Scope :

Internet/GSM connectivity at site. OSPCB registration and login credentials.

TI-C-001

Plant Access Road

Access road from existing plant road network to new SAP plot boundary.

Existing Plant RoadNew SAP — Plot Boundary
Size:7.5m wide (2-lane)
MOC:Bituminous / CC road
Design:Heavy vehicle rated (60 MT)
EPC Scope:

Internal roads within SAP plot — all paved roads, pipe rack crossings, equipment access.

Client Scope :

Access road from existing road to SAP plot boundary. Any modifications to existing road for heavy transport during construction.

TI-C-002

Storm Water Drainage

Storm water drainage from new SAP plot to existing plant drainage system / outfall.

New SAP — Plot DrainageExisting Storm Water Drain
Size:600mm RCC pipe
MOC:RCC NP3 class
Design:Design rainfall: 150 mm/hr
EPC Scope:

Internal storm water drainage within SAP plot — catch pits, drains, oil interceptor.

Client Scope :

Connecting drain from SAP plot boundary to existing storm water system. Augmentation of existing system if required.

TI-EF-001

Acid Effluent to ETP

Acid-contaminated effluent from SAP (equipment wash, spills, first flush) to existing ETP.

New SAP — Acid Effluent SumpExisting ETP Inlet
Size:4" NB
MOC:HDPE / PP-lined CS
Design:pH 1–3 / Ambient / 10 m³/hr max
EPC Scope:

Acid effluent collection within SAP plot — sumps, pumps, neutralization pit (lime dosing), pH correction to 6–9 before discharge to battery limit.

Client Scope :

Effluent pipeline from battery limit to existing ETP. Augmentation of ETP capacity if required.

TI-EF-002

Sanitary Sewage

Sanitary sewage from SAP control room, lab, and welfare buildings to existing sewage system.

New SAP — Septic TankExisting Sewage System
Size:6" NB
MOC:PVC (SWR grade)
Design:Gravity flow / 5 m³/hr
EPC Scope:

Sanitary drainage within SAP plot, septic tank, soak pit (if no existing connection).

Client Scope :

Connection from SAP septic tank outlet to existing sewage system.

Tie-in Summary — Acceptance Status & Cost Impact

Tie-in IDServiceCategoryCriticalStatusCost Impact
TI-P-001Molten Sulphur FeedProcessYesAccepted
TI-P-002Product Acid (98.5% H₂SO₄) DispatchProcessYesAccepted
TI-P-003Oleum (20–25% SO₃) DispatchProcessNoAccepted
TI-P-004HP Steam Export (40 bar, 400°C)ProcessYesAccepted
TI-P-005LP Steam Export (4.5 bar, saturated)ProcessNoAccepted
TI-P-006BFW Return (Condensate)ProcessNoAccepted
TI-U-001Cooling Water SupplyUtilityYesAccepted
TI-U-002Cooling Water ReturnUtilityYesAccepted
TI-U-003DM Water SupplyUtilityNoAccepted
TI-U-004Raw Water SupplyUtilityNoAccepted
TI-U-005Instrument Air SupplyUtilityNoAccepted
TI-U-006Nitrogen SupplyUtilityNoAccepted
TI-E-001HT Power Supply (33 kV)ElectricalYesAccepted
TI-E-002Power Export (TG Output)ElectricalYesAccepted
TI-E-003Emergency DG PowerElectricalNoAccepted
TI-I-001DCS Integration with Existing PlantInstrumentationNoAccepted
TI-I-002CEMS (Stack Emission Monitoring)InstrumentationNoAccepted
TI-C-001Plant Access RoadCivilNoAccepted
TI-C-002Storm Water DrainageCivilNoAccepted
TI-EF-001Acid Effluent to ETPEffluentNoAccepted
TI-EF-002Sanitary SewageEffluentNoAccepted
TOTAL ADDITIONAL COST IMPACT0 rejected₹0

Note 1: Cost impacts are indicative estimates based on similar projects and will be finalized during detailed engineering. Actual costs may vary based on site conditions, routing distances, and existing facility modifications required.

Note 2: For critical path tie-ins (marked in red), rejection by client may result in schedule extension of 2–4 weeks depending on the scope of additional work. This will be assessed during detailed planning.

Note 3: All tie-in points are defined at the battery limit flange (for piping) or cable termination (for electrical/instrumentation). The EPC contractor's scope is strictly within the battery limit unless specific tie-ins are rejected by the client, in which case the scope extends to include the client's portion at additional cost.